John Deere – 1023E, 1025R and 1026R – Pump Flow Test (Tractors With SCV)

Reference

→NOTE:
The following tools may be required for proper diagnosis:
1. JT03051 (Part of JT05418—Industrial Flow Test Kit)
2. JT03042 (Part of JT05418—Industrial Flow Test Kit)
3. AR94522 (Internal Half)
4. JT07148
5. Hydraulic Hose 1-1/16 F 37° x 1-1/16 M 37° (2 used)

( 1 ) Install Test Equipment

Action:
[1] – Assemble test equipment and connect flowmeter inlet hose to one of the SCV couplers.
[2] – Secure flow block return hose into transmission/hydraulic fill hole.

Result:
YES: Go to Procedure 2.

( 2 ) Pump Flow Test (With SCV)

Action:
[1] – Warm hydraulic oil. (See Hydraulic Oil Warm-up Procedure in this Group.)

[2] – Fully open JT07148 Digital Hydraulic Tester control valve.

[3] – Start tractor and run at 3200 rpm.

[4] – Slowly close JT07148 Digital Hydraulic Tester control valve until 10 345 kPa (103.5 bar) (1500 psi) shows on the gauge.

[5] – Record flow, then open JT07148 Digital Hydraulic Tester control valve to release pressure.

[6] – Compare recorded flow with specification below.

Result:
YES: Return to diagnosis in progress.
NO: The mesh filter may be restricted.
NO: Filter/manifold may be restricted.
NO: The suction line may be restricted.
NO: The suction line may be leaking air. Check clamps, hose, and O-ring on suction line.
NO: Relief valve may be leaking.
NO: Control lever or cables not allowing full open valve.
NO: Coupler damaged. Repair.
NO: SCV valve spool scored or leaking.
NO: Mechanical hitch valve spool scored or leaking.
NO: The pump may be worn or damaged, requiring repair or replacement.